Friday, September 18, 2009
No strong visuals for Day 5, the crew finished framing the interior walls and the vaulted ceiling in the master bedroom. They also completed the roofing and flashing on the outside. Essentially, there was much prep work to ready the house for next week's big events... plumbing, electric, siding, and anything else they can fit in.
Now that the house is taller, it became quite clear that some branches needed to be trimmed on our big tree - they were hitting the new front windows. So we took care of that this weekend. Also, Steve (architect/general contractor) let us know that we need to select our bathroom tile and tub color. Our first visit to a showroom - exciting!
Sunday, September 20, 2009
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment